  PROJECT TIMETABLE (Revised):  
 
Overall duration of the project: 12 months

 
  # / Activity / Period  
 

1


Project design:
- Development Methodology
- Reading

Training

March - May 03

2


Completion of the research project design (adjustments):

Training

June 03

3


Data collection In-field research

Training

July - September, 15

4


Submission of interim report


August 03

5


Analyzing of the collected data

Training

September - October 03

6


Drafting of the Research and Policy Papers

Training

October - December 03

7


Mentors Revision of Policy and Research Papers


January 04

8


Completion of the research paper and policy paper


February 04

9


- Distribution of the discussion paper drawing based on the research paper
- Conduction of a discussion group for independent policy analysts, researchers, local think tanks representatives, in-house researchers etc, led by the Central Asian Institute for Development
- Distribution of Policy Paper


Training

March 04